Hi,

I am looking to configure the settlement of production order variances to cost centers/internal order. Is there a way to do this in the settlement profile. Would appreciate your help.

Thank you,

Ram

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

OKO7 will allow you to configure the Settlement Profile by selecting valid receivers.

This should be done with/or by FICO.

Then test, test, test

award points if helpful