Production Order Release

Former Member
0 Kudos

Can any tell me where in the IMG the Production order release is maintained?

Kind regards.

Guy.

Accepted Solutions (1)

Accepted Solutions (1)

siddheshwar_rajguru2
Active Participant
0 Kudos

Hi,

REL productio oredr can be make automated after creation of prd ored

i.e in OPKP - production scheduling profile

After CRTD ---> REL prd orde.

or else you can make REL mannully in CO02 -->change prd ord

Normally it is mannully REL , coz REL staus is business activity done by responsible person from production department- like Executive level person.

Once it is REL goods movement done GI .

and ready for confirmation of order.

Regards

Siddhesh

Answers (8)

Answers (8)

Former Member
0 Kudos

Hi,

Youhave to go in change mode of the order Co02 and then go to the opeartion overview...select the operation to want to release and press the buttom released .

Your selected operation will be released.

If you want collective release then go for the CO05N transaction...select operations and profile and give the selection criteria...from here you can release the operations collectively.

Regarsd

former_member184655
Active Contributor
0 Kudos

Dear Mr.Guy,

So many good answers,please reward points to all the helpful answers and also

dont forget to close this thread as answered.

Regards

Mangal

Former Member
0 Kudos

Hi,

You can release the production order either manually or automatically.

For Automatic release:

This can be done via production scheduling profile.In this profile we can

decide whether the orders created can be released automatically or not.

For manual release :

open the production order and click the green flag symbol.

with this the orders will be released.

If you want to release operation wise goto op overview,choose the operation and now click the green flag.This will release the particular operation.

Using Triggerpoint:

By using the trigger point assigned to particular operation in the routing we can decide the next operation is to be released when the status of this operation changes.

Regards,

nandha

Former Member
0 Kudos

Hi

Using production scheduling profile u can define that when the production order to be released, it is released while creation automatically

former_member184655
Active Contributor
0 Kudos

Dear Mr.Hall,

<b>If you want to release your production order enter the production order no in T

code CO02 and hit on the flag seen at the extreme left hand side and save the

order.</b>

As per settings in SPRO,if u have made the availablity check as a must and if

missing parts are there (deficit of raw materials)

dont allow release of production order,then the order cant be released.

If useful reward points.

Regards

Mangal

Message was edited by:

Mangalraj

Former Member
0 Kudos

Hi

This you can maintain in OPKP transaction(prodn scheduling profile)

Regards

Ranga

Message was edited by:

Ranganathan Srinivasamurthy

Former Member
0 Kudos

Hi,

Production order can be realease after creating in production scheduling profile, in automatic actions after creation.

Regards,

Suhas

Former Member
0 Kudos

Hi Guy,

Goto Co02 and click the flag, it will release the production order

if you need automatic relase then set in production scheduling profile

reward if it solved

Thanks

bala