Production order Plan Price

Former Member
0 Kudos

Hi,

Can anyone tell me from where the plan price in the Production order cost analysis sheet is coming from in case of moving average price? whether it is the production start date/end date/release date/confirmation date

TIA

Sabitha

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Go to OPL8 for the order type - plant combination & in cost accounting view, you will find a field called costing variant planned.

Now go to OPL1, double click on the costing variant planned as seen in OPL8 & identify the valuation variant. Click on the push button of valuation variant, it will take you to the details. Here in the material val. tab you will get the sequence in which the price is picked. The price is then multiplied with the bom qty to arrive at the planned price.

Regards,

Vivek