Hello,

I want to block the possibility of creating of production orders in the moment when en error 048 appears (The consumption account found in order to automatic account determination for material u2026. does of exist notes for the date u2026. specified.)

Currently error CK 048 even though has the type u201D E u201E isn't blocking creating orders.

What can I do?

Artur

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member566378
Participant
0 Kudos

Yes I have " split valuation" but these materials aren't participating in production order.

For tests I created "split valuation" for one component and... still I could create the order.

Artur

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Do you have split valuation there?

Please check have you maintained the price for the splitted material in MM02.

Regards,

R.Brahmankar