Hi PP Gurus,

I want to getting the production order list which was already cost calculated (Standard cost, Planned cost and actual cost) between two date (e.g 01/09/2019 to 23/09/2019)

Which is date preferred from table data (actual finish date - AFKO, Posting date - AFRU) ? any other option to getting a production order list through date ?

Thanks and Regards,

Rohit

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Did you check the report KOC4? Which has selection based on dates like Scheduled finish, which will provide you a list of orders.

Or check table COEP by object number OBJNR from production order table AUFK given the field AUFNR.

Best Regards,

R.Brahmankar