Hi chenchunyan

The entry for 'Change Documents for Networks and Orders ' is the correct one to use . Please select this , or input ORDER directly into the field Change Document Object . The results will be the same

Best Regards

Enda

cindychen
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Enda,

Thanks for your reply, but I cannot load the change record even I made a change on an order just now. Is there any other action to active the change record before I change the production order?