Friend,

I am not able to branch to cap. planning table from production order screen. (using goto menu). System is not giving any message.

What could be the reason?

Accepted Solutions (1)

Accepted Solutions (1)

former_member184627
Active Contributor
0 Kudos

Hi,

Also you need to select dep. cap. reqmnt in the control key.Eg(PP01/PP02)

T.code op67.

Regards,

SDS

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

you can check with transction OPJK and activate the capacity scheduling indicator.

Regards,

Mohan R

Former Member
0 Kudos

Hi Sandeep,

do the setting for finite scheduling then only it will show,

you need to assign in spro order control in OPJK make sure capacity check is active and overall profile you haev given for that

Thanks

Bala

Former Member
0 Kudos

You want to do capacity planning,Please check finite scheduling check box in the work center field