on 2024 Dec 02 4:47 PM
Hello Experts,
We have two process orders which are having DLV status set on 24.11.2024 which falls on P11. We ran the job's for collective order settlement on 25.11.2024. The variances for these two orders were not calculated and in result the orders were not settled. When we ran the collective settlement on 30.11.2024 which falls in P12, these orders were settled. My question here is the DLV status was set in P11 still why system has not calculated or settled the order when we ran the settlement process on 25.11.2024.
Any help will be highly appreciated, Thanks in advanced.
Request clarification before answering.
The settlement job can settle orders that were delivered after the job started but before it finished. This is because the system processes transactions in real-time and updates continuously. So, even if the settlement job started at 01:00:00, it would still include orders delivered up until 17:15:00, as long as the job was still running.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
59 | |
8 | |
8 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.