Hi

In Process order we are using Operation & Phases in master recipe.

Standard values are giving to phases only.

Individual Confirmation (COR6) are performing using Phases only..

Process instructions are also giving to phases only.

For creating phases operation is required( superior operation)

Just i want to know where these operations will be used in a process order other than this.

I want to know the difference between Primary & Secondary resource and their application in Process order..as these terms are not there in REM/Discrete Mfg..

Regards,

srihari.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello Shrihari,

What you have observed is right.

In process order processing we need to use the phases instead of operations in production order eg. when you want to do the partial confirmation, you need to do it for the phases and not the operations.the GI of components( if attached to the Phase )will then take place at that time.

About primary and secondary resources I can give you a practical example.

If you consider a washing machine as a resource then it has two parts the Wash tub and the drying tub. You can consider the washing machine as the primary resource and the washing tubs and drying tubs as secondary resources of the washing machine.

Hope this helps you.