problems in project cost settlement

Former Member
0 Kudos

We have large projects . While running CJ88 total cost is not settled in one run . we need to run cj88 2-3 times then total cost is settled. Some times even after running 2-3 times we find some unsettled cost. What can be possible reasons.

Accepted Solutions (0)

Answers (1)

Answers (1)

narasimhulu_konnipati
Active Contributor
0 Kudos

You can do the mass settlement through CJ8G.

First create the Variant with details of Project, Network and WBS Element.

Then do a test run

Thne run it in Real mode

Hope this helps you

Thanks

Former Member
0 Kudos

we are doing one project at a time in cj88 with test and then update run .

narasimhulu_konnipati
Active Contributor
0 Kudos

Even with CJ8G, you can settle one by one.

Moreover, you can run this background which will take less time compare to CJ88

There is not mandatory that you have to select many in CJ8G.

Select one project and run, it will help you in time consumption

Thanks