Hello,i hope that u are fine ?

i have an issue with the price during creation of PO.

first i have a contract ,juste we have a new price with the vendor,so i decided to add another price with another validity period in item post/conditions after that i saved it.

in ME01 i use this contract as a source fix.

after that while i am creating the PO it gives me the price of info record .

is there any solution to solve this issu .

former_member183424
Active Contributor
0 Kudos

Show the screenshot with each validity period of contract, PO date, info record.

Accepted Solutions (0)

Answers (2)

Answers (2)

JL23
Active Contributor
0 Kudos

Make sure that the contract is valid for the PO creation date and not just for the delivery date, a contract that is not valid at the PO creation date is ignored as source.

Prasoon
Active Contributor
0 Kudos

Hi,

Go to M/06 and check the access sequence assigned to the gross price condition in PO (for example, PB00 in standard). Now, go to M/07 and make sure that the table contract item price table 016 is having a higher access step than the Info-record table 017 as shown below. Also ensure that there is no 017 table repeated above 016 table in the access sequence.

Test the scenario again with a new release order and revert back.

Regards,