I am having problem with IT2002 activity allocation, Required values are not
filled  through CAT6. Could you let me know how to activate activity
allocation in IT2002

   

Regards

Devi

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello Devi,

Please check the below:

  1. 1. Please check IT0315 Cost accounting variant.
  2. 2. cross verify the Activity type is recorded against your CATS->HR entries in CAT2
  3. 3. Check the integration is active between time mgt & CO/PS etc in IMG configuration
  4. 4. Check in IMG-Time Management-Integrating Time Management with Other SAP Applications-Permit Integration for Infotypes-Recording Specifications for Activity Allocation and its subtypes
  5. 5. Check and activate COBLT feature.

Hope with the above checks you can succssefullly move the activity type to cluster B2