Problem in planed quantity for production order using MRP

Former Member
0 Kudos

Hi Expert,

There is a problem occured when we create the production order and purchase order of a final item using the MRP Order Recomendation

Parent Planed Qty

P0001 4320

Base Qty PlnQty by Sap Actual Qty

Child 1 0.166667 720.00144 720

Child 2 0.020833 89.99856 90

Child 3 0.066667 288.00144 288

Child 4 0.01041 44.9712 45

Child 5 0.166667 720.00144 720

When i enter the minimimum order quantity and order multiple quantity is 1 then MRP Order recomendation generate some quantity for purchase order correct but some like child 1 incorrect (721 instead of 720) and when i create the production order with this MRP Recomendation it again generate the planed quantity wrong(720.00144,89.99856,288.00144 etc) for child item.

Thanks

Rahul

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Expert,

There is a problem occured when we create the production order and purchase order of a final item using the MRP Order Recomendation

Parent Planed Qty

P0001 4320

Childitem BaseQty PlnQtybySap ActualQty

Child 1 0.166667 720.00144 720

Child 2 0.020833 89.99856 90

Child 3 0.066667 288.00144 288

Child 4 0.01041 44.9712 45

Child 5 0.166667 720.00144 720

When i enter the minimimum order quantity and order multiple quantity is 1 then MRP Order recomendation generate some quantity for purchase order correct but some like child 1 incorrect (721 instead of 720) and when i create the production order with this MRP Recomendation it again generate the planed quantity wrong(720.00144,89.99856,288.00144 etc) for child item.

Thanks

Rahul

Edited by: Rui Pereira on Apr 30, 2009 5:02 PM

former_member204969
Active Contributor
0 Kudos

It is clearly the consequence of the 6 digit precision of the base quantity, and the method the system uses to compute the actual quantity through the base quantity.

(I think in he BOM there were the components defined for 3*n product, and the system rounded when computed the base quantity.)

Answers (0)