problem in miro

Former Member
0 Kudos

hi

when i am doing MIRO of planned delivery cost i m getting the following error

service is being revised and is locked

message no /EACC/MSG_ACC_COMP001.

please suggest the possible solution.

Regards,

Vijay

Accepted Solutions (0)

Answers (1)

Answers (1)

pankaj_singh9
Active Contributor
0 Kudos

Hi,

Go to SPRO > MM > General Settings for Materials Management > Set Up Material Block for Invoice Verification >

In this step, you specify at what point materials are blocked in Invoice Verification:

o During the allocation phase, all materials present in the invoice are blocked.

o During simulation or posting, materials whose stocks are to be changed are blocked and are read again.

o Materials whose stocks are to be changed, are blocked and are read again when you post.

Someother user might be using the same material for transactions.