Dear All,

I have a very complex pricing scenario related to BOM material.

Price is calculating on the component level, and accumulating on the main component level, and main component level price will accumulate on thcapture-2.pnge main finish product, call finish material, all the BOM items are below this.

Looking for the gurus feedback.

Accepted Solutions (0)

Answers (2)

Answers (2)

ankurch
Active Contributor
0 Kudos

Hello Imran,

So what is the problem, because I am not able to see you are facing any issue to do this, all you have to do is create multi level BOM.

Thanks,

Lakshmipathi
Active Contributor
0 Kudos

What efforts you have taken so far and what the issue you face while trying ?

former_member301027
Participant
0 Kudos

Dear G Lakshmipathi,

System not accumulating the values on the main material of BOM, that is the issue, all values are updating at the header level of the sales document.

Ref. to excel exampe, item 30-40 values not accumulating at the line item 20, and all the line items of component values are not accumulating at the line item 10.pricing-2.png

Please share your valuable feedback, regards,