Hi dudes,

in preventive maintenance, I have created suitable time-based package, task list and then planned it in IP42.

I want this maintenance tasks tobe done on non-working days weekly so I set start cycle on a non-working day and the period time is & days.

when i run IP10 everything is ok and all call dates are on weekend(for example 26.05.2010), but when it gets to planed date and the order creates the date is the next day (27.05.2010). I deleted factory calendar from the work center and the scheduling indicator in maintenace strategy (IP11) is* time* (not ) time-factory calnd .

what can I do? is it standard of SAP that doesn't let PM orders being created on non-working days?

thank you in advance

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Create a Factory calander with non working days & assign that in Maintenance Strategy. Try this one.

Regards,

Maheswaran.

Former Member
0 Kudos

it helped Maheswaran thanks alot

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Danial,

i think you would select "Time for factory calendar" in maintenance strategies and make sure preventive-order's work-center have a same calendar with maintenance strategies

Former Member
0 Kudos

Hi,

If i create a factory calendar base Strategy, preventive orders just can be created on working days that are defined in that calendar. what I want is on the conterary.

former_member546319
Contributor
0 Kudos

Hi Danial,

Maintain the same Calender in the Work center in Capacities Tab which you have maintained in the Maintenance Plan.

This should help.

Regards,

MLN Prasad

Former Member
0 Kudos

Hi dude,

i am using a time base strategy (IP11) that doesn;t need factory calander so I deleted this field in related work center. but it still doesn't create orders on non-working days.

my question is how it could understand which days are working and non-working days???