Hi All,
whats Pre requisite setting required for source inspection.?
Thanks,
sid
Request clarification before answering.
hi,
Pre- Requisite are:
maiantain 01 / 0101 in Material master , and active preferred and active indicator .
Goto QI01, maintain Release Untill date, goto inspection tab, enter 01/0101 in source inspection type and lead time like 15 days or go as per ur requirement, u may tick or not it depends on ur requirement on "Source inspecction- NO GR."
and save ur setting .