PR Workflow

Former Member
0 Kudos

hi guys

as per img path

1.mm->purchasing-> rel proc->with classification

i did all this

1.Rel Grp

2.Rel Code

3.Rel Ind

4.Rel Strategy

5.Work flow

still i did

2. edit org plan

3.SAP net weaver-> Bus Management->Work Flow-perform task specifg customisation also

4.activating event

still work flow is not working.

but rel strategy is triggerd at ME29n.

can u please explain me

what all additional steps i should take other than MM module configuration steps.

plz

nani

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Check characterstic manitenence and values in tcode CL24N.

Former Member
0 Kudos

hi

i did cl20n,cl24n also

still am not getting

can u plz explain me workflow settings other than MM module

Former Member
0 Kudos

First of all you need start up workflow system, you need run automatic workflow customizing by SWU3.

And then check if you assign the tasks to the agents, in your case, YOU.

And then you need activate the event link of your workflow.

FYI.

[http://help.sap.com/saphelp_erp2005/helpdata/en/04/926f8546f311d189470000e829fbbd/frameset.htm]

You can check in SBWP to find if you received workflow in Inbox.

You can monitor workflow running by SLG1 and SWEL.

You can find all the tools in the sap menu Tools->Business Workflow.

About MM workflow plase refer:

[http://help.sap.com/saphelp_erp2005/helpdata/en/33/4c9a34272a5f2ee10000009b38f83b/frameset.htm]