PR triggered by the project

Former Member
0 Kudos

Dear all experts,

please help me on the following issue.

i assign a material to an activity, release the project and run mrp, i get the PR for the material.

i need the PR document type be ZPR, not the standard NB.

i enter ZPR in OPTT, but it doesn't work.

do i need to do anything else?

can i set the material PR type to be ZPR?

thanks a lot.

Judy

Accepted Solutions (1)

Accepted Solutions (1)

nitin_patoliya
Active Contributor
0 Kudos

The same you need to define at IMG>Materials Management>Purchasing>Purchase Requisition>Define Document Types.

Then it will reflect in OPTT & you can assign there.

With Regards

Nitin P.

Former Member
0 Kudos

thanks Nitin.

what i mean is i have defined ZPR in MM and assgin ZPR in OPTT.

but the material PR type i got after project MRP run is not ZPR, but NB.

is there something wrong? do i miss something?

thanks a lot.

Judy

Edited by: Judy ZHU on Nov 17, 2009 1:12 PM

former_member203108
Active Contributor
0 Kudos

Have you completed allowed item categories for your new document type?

Former Member
0 Kudos

Hi,

I dont think it will take this no range because this PR is created after MRP Run not through Project.

Muzamil

Answers (0)