Dear MM Consultants,

I have create Release Procedure in Dev Client when I move Reuest to Quality Server . Edit characteristics,Edit Classes,

Set up Procedure with classificaton . we can create Characteristics and classes by using CT04 and Cl02 but how to set

up procedure with classification in Quality server and production servers in ECC 6.0.

Regards

Dnyaneshwar.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

For transporting of release strategies please check note 86900 and 134559.

The classification data need to be transported by ALE as described in

notes 86900 and 45951. The only other solution is to enter the data

manually.

There is another possibility that you could take into consideration for

the classification is to import them via batch input:

RCCTBI01 for creating characteristics

RCCLBI01 for creating classes

RCCLBI03 for classification"

Regards,

Ashwini.

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

first create Class and Characteristics in quality after move the TR to Quality

check in cl20n, cl30n and cl24n.

Regards

Raj

uk_yelamuri
Contributor
0 Kudos

Hi,

After creating the release characteristics and class in quality, you can use CL20N to enter the classification values for release strategy.

By that time, your TR with release strategy should be moved to quality. Only classification data with in release strategy should be entered in each client.

Former Member
0 Kudos

As far as I can understand your question, you need to create Characteristics, Classes etc before moving TR to Quality. And after moving TR to Quality, all your configuration will be ready for use. Please let me know what is exactly missing and what issue you are facing?