PR delivery date

Former Member
0 Kudos
179


If PR is created through MRP on yesterday & delivery date is suggested 12th Feb. & If I am creating po of this PR today tehn delivery date is shifint to next date.

How can I can stop this. Does clicking on fixed id in PR will not shift del date to next date?

Thanks,

Kiran

Accepted Solutions (0)

Answers (4)

Answers (4)

JL23
Active Contributor
0 Kudos

The OSS note 493315 - FAQ: Purchase requisition (general)   explains in Q13 that the delivery date is copied 1:1 from a PR to a PO.

Can it be that there is any BADI that affects the delivery date in your case?

Former Member
0 Kudos

Hi,

Please check in OMEW tcode along with plant purchase process time, you create PO with reference to PR or not

former_member183424
Active Contributor
0 Kudos

PR delivery date is depend on PR processing time..

OLME- Purchase Requisition-Processing Time

And also the same delivery date is carry on in PO, if you create the PO with reference to this PR.

Former Member
0 Kudos

Did you maintain any GR processing days in Purchasing view for material, if so might be this is calculating as such.