PR Check Avl Option Not Working

Former Member
0 Kudos

Hi

While am creating PR thro ME51N, i need to chk the matl availability..

I can see the icon in PR creation time...

While clicking its not showing the stock..

Advice me the SPRO settings required for this..

Vijay

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member660933
Active Contributor
0 Kudos

Hello,

Please check the following :

1.Create checking rule for Stock transport requisition.

2. Define checking rule for Stock transport requisition.

3. Assign checking rule for Stock transport requisition.

4. Maintain the "Availability check" field in the view "Material Requirements Planning 3" for the product / plant combination specified in the material master for supplying plant.

Regards,

Shailesh

Former Member
0 Kudos

Hi

Whr it is avl in SPRO

Pls explain in details

Vijay

Former Member
0 Kudos

?