PP Work Center in SAP Plant Maintenance

ashish_singhal90
Participant
0 Kudos

Hello All,

Hope you all are fine.

In PP, work center is machine or labour on which production occur.


What is the relation of PP work center with Plant maintenance and where does it effect?.


Please throw light on this topic and share your knowledge.


Thanks & regards,

Ashish

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Ashish,

Main work centre is for Plant maintainance  is nothing but a labor or group of labors  responsible for maintenance of that particular equipment.

You can use PP work center on location tab of a Equipment/functional location. Its generally of category other than 005.

So in prospective of plant maintenance, PP work center can be represented in technical object master data in Location tab.

Regards,

Amol

ashish_singhal90
Participant
0 Kudos

Hi Amol,

Thanks for reply.

We can maintain the PP work center in location tab but what is the exact use of maintaining PP work center FL/equipment master.

Please elaborate this.

Thanks & regards,

Ashish

MTerence
Active Contributor
0 Kudos

Hi Ashish,

Refer below thread for clear understanding

question on work center field in equipment Master | SCN

Regards

Terence

Former Member
0 Kudos

Hi Ashish,

This PP work center is comes in picture in reference to capacity planning for production.

Meaning, if technical object ( FL/EQ) is being used for running production. & if a maintenance work order is created for this technical object, you have an option to select the system condition for this technical object.

1) In operation - Production work can be continued

2) Not in Operation -  Production work can not happen until maintenance is over.

If you select system condition as NOT IN OPERATION, it will result in PP work center commitment & capacity load records will be created for this work center.

Regards,

Amol

Answers (3)

Answers (3)

dimasluis_defaria
Active Participant
0 Kudos

Hi Ashish,

This integration of PP and PM, is much more important for PP.

If in your equipment, you put a work center of PP.

When you create the maintenance order (and to put system condition = Not in Operation), inside of the planning of capacity of PP, the time of maintenance, it will be unavailable for the production planner to program production orders

It is only interesting this, if in your company to use CRP PP (capacity planning).

When it will test, to ask for the person of PP, to show  CRP PP

Regards

Dimas Faria

0 Kudos

Dear Ashish,

Refer below thread which has similar query as you have.

Hope it solves your query.

Thanks & regards,

Shiv

Former Member
0 Kudos

hey there,

Please have a look at this document:

From my experience the PP Work Centre in PM was used for integration between SAP PM and PP / APO to determine resource (machine) availability to plan maintenance.

cheers,

K