PP_Reservation quantity

Former Member
0 Kudos

Dear Friends,

I have released my production order. So based on my BOM the system creates reservation for my order. Let us assume my reservation quantity as 100 each.

While i am confirming my ordeer in CO11, in the goods movement, the user wants to enter 110 each ( 10 pieces more than reserved quantity). I am having enough stock in my store. But this particular item getting failed while confirming the order.

If i go to transaction COGI, i am getting INFORMATION (not error) as

" Reserved quantity is exceeded by 10 each"

HOW TO MOVE THIS QUANTITY 110 for that order?

Thanks

Senthil

Accepted Solutions (1)

Accepted Solutions (1)

former_member196398
Active Contributor
0 Kudos

Hi Senthil,

Just change the component qty to 110 in change mode of the order and save. Once that is done, you can clear the COGI error record.

Regards,

Prasobh

Former Member
0 Kudos

Hi Prosobh,

Thanks.. I have awarded u full points..You have not answered my PP_varince calculation query

Senthil