cancel
Showing results for 
Search instead for 
Did you mean: 

Post goods movement after revoking TECO

former_member445197
Participant
0 Kudos

Hi All,

I have followed the steps in the below blog to prevent the following transactions when Production Order status is technically completed (TECO):

1. Production order confirmation

2. Posting goods movement

3. Cancel production order confirmation.

Link to the blog:

https://blogs.sap.com/2015/02/25/preventing-goods-movement-and-confirmation-to-processproduction-ord...

However, even if I revoke TECO, I'm still unable to post goods movement from the order confirmation screen due to the error message "Teco Done!".

Please advice on how to allow production order confirmation and goods movement when TECO is revoked.

Thanks.

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

I have never seen this error message "TECO DONE". Are you sure it is an standard message? What is the message ID and message number?

This document will help you to find where this message is triggered:

https://archive.sap.com/documents/docs/DOC-53035

Regards,

Caetano

former_member445197
Participant
0 Kudos

Sorry, it didn't occur to me that it might not be a standard message. I'm unable to find the message number because clicking the error on the status bar doesn't bring up a pop-up with the message number. I'll check where the message is triggered and get back to you. Thanks so much for the document.

former_member445197
Participant
0 Kudos

Hi Caetano, the issue is resolved. The error message was not a standard message. Thanks so much for your help!

Answers (0)