cancel
Showing results for 
Search instead for 
Did you mean: 

PO warning message

Former Member
0 Kudos
461

Hi.

When I first time change the PO delivery date and press enter without save the PO, system will display warning message base on SAP calendar setting. Let say 1st, 2nd and 3rd September 2008 is already set as non working day and 4th September 2008 is a working day. So for the first time if I choose 1st September and press enter system will display below warning message:

Delivery date: next workday is 04.09.2008

But when I change the date to 2nd September 2008 and press enter, system will not display above error. My question is this scenario base on SAP Standard?

Thank you.

View Entire Topic
dhrubacharan_behera
Active Contributor
0 Kudos

Hi,

In comaparing the delivery date the system uses the factory calendar ,not holiday calendar.If in the factory calendar the delivery date is a holiday and the next day also is a holiday when you enter the date in the PO message will appear first time for each delivery date if it is a holiday.In your case check the factory calendar settings and if the next day is a holiday it should display the message no.ME080 .This I observed .

Dhruba

Former Member
0 Kudos

Thanks for the answer!