PO - Schedule Date

Former Member
0 Kudos

HI all

I have one query regading Schedule date (Purchase order).

While creating PO , CUSTOMER fills the schedule Date for ITEMS to be delivered.

Now when Vendor Sends confirmation,He states DELIVERY date in confirmation.

How many days difference is possible/allowed in SCHEDULE DATE and DELIVERY date.

For example: if SCHEDULE date is 12th NOVEMBER 2006

WHAT could be last possible DELIVERY DATE that a vendor can fill while confirming for that PO?

Thanks in Advance.

Vijay Raheja

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Viajay,

I don't think SAP have any real control over the delivery date specified by the vendor.

It can not be enforced in a standard system.We can use user exits to control this behavior.

SAP has given the user exit to determine Earliest Delivery Date (GR Check (PO Only) ) EXIT_SAPLEINR_004 at the time of GR.

Hope this helps you to some extend.