Hi expert,

My client would that the planned service line inserted in the new Service entry sheet, doesn't exceed the value of the related service line inserted in the correspondence Po

Thank you in advance.

Regards.

View Entire Topic
Prasoon
Active Contributor
0 Kudos

Hi,

   Your question is not fully clear. The price in SES can be changed for planned services only if the "price change" indicator is flagged in the PO - service item. If you dont want the service price to be changed in SES, you may remove the flag / hide the field from the PO using the field selection in ML91.

   Other option would be to change the total price of services by increasing the SES quantity, which can be restricted by the system message SE 363

   Revert back if your question is different.

Regards,

AKPT

former_member249754
Participant
0 Kudos

Ho

In the po the price can be changed because the related flag has been set. My problem is the value in the Ses could be greater than the value of the po service line.

Thank you

Prasoon
Active Contributor
0 Kudos

Hi,

   As of my knowledge, there is no validation between the PO - service item price and SES item price in standard. You may check the feasibility of development!

Regards,

AKPT