Could you tell me how to create PO for Project and Goods Receipt in Project Stock.

Thanks and Best regards,

Thang

Accepted Solutions (1)

Accepted Solutions (1)

csaba_szommer
Active Contributor
0 Kudos

Hi,

1.

You can create a PO in ME21N with account assignment category "Q". You have to give the WBS on the account assignment tab (at item level).

2.

Other option is to run MRP and to convert the PurReq generated by MRP into PO (if you get PldOrd first you have to generate it into PurReq).

This works if master data settings are maintained properly (Procurement type on MRP2 view of mmr, individual/collective requirement indicator on MRP4 of mmr, etc).

If your PO has a project item it gets to project stock automatically when you do GR, you don't need to do anything special.

Regards,

Csaba

Former Member
0 Kudos

Hi

Thank you for your answer.

Could you please tell me what difference between account assignment category "Q" and "P".

Regards,