Hi All,

Can anybody tell me in PM, how available capacity for PM Work Centre is calculated?

For example:

Calculate available capacity for work center

In PM, a work center contains the following, and please calculate the available capacity ?

Start time : 05:00

Finish time : 08:00

Length of break : 01:00

Capacity Utilization: 100

No. of individual capacity : 1

Regard,

SAP PM

Accepted Solutions (0)

Answers (1)

Answers (1)

sebastian_lenartowicz
Active Contributor
0 Kudos

To my mind this would be:

((Time from start to finish)-(Break time))*(Capacity utilization/100)*Capacities

In your example, I believe that'd be

(3-1)h*100%*1=2h