PM Orders / Termination of positions

Former Member
0 Kudos

Hi Experts!

I face a problem in our system, maybe you can help me with our orders.

Our erliest start time of position 0020 is always in relastionship with the end time in position 0010. I gues it is not a big thing, but i cant find the seetings in the customizing.

Best Regards

Florian

Accepted Solutions (1)

Accepted Solutions (1)

jogeswararao_kavala
Active Contributor
0 Kudos

Hello Florian,

You need to do it manually through Relationship settings in Operations detailed screen like below.

If you know this and want to automate, then you need to go for a code in suitable user-exit or BAdi.

Regards

KJogeswaraRao