Hi,

I want to settle PM order plan costs to Cost Centers for correct Standard Cost Calculation. But system issues that this order is not relevant for "Integrated Planning". In PM order type customizing there is no check box for "Integrated Planning". Is there any other way to transfer planned Maintenance costs to Cost Centers?

Regards,

Elvin Bekirov

View Entire Topic
peter_atkin
Active Contributor
0 Kudos

Elvin Bekirov

Planned PM/CS order costs on cost centres does not look to be availble (see TCode KOT2).

Open an OSS Message to SAP to see what they recommend.

PeteA

ben_lerch
Explorer
0 Kudos

Hello Elvin

Did you get an answer from SAP or were you able to settle plancost from PM/CS order?