Please give me the solution for the below scenario

Former Member
0 Kudos
62

1.We will raise the quantity contract of white material of 3, 00,000 quantities for the year.

2.Then we will raise the PO with the reference to the above quantity contract of 50000 quantities with the different material code than quantity contract.

(We will purchase the white material from the same vendor & same material will get printed (in terms of colour or design).(So in the Qty Contract: Material code will be for white material and in the PO: Material Code will be for Design or Print.)

3.There will repetition of point no.2 in terms of quantities till the qty mention in Quantity contract is exhausted.

4.Migo & Miro to settled based on the point no.2

Regards,

Anant

SAP-MM Consultant.

9920461009

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

use the concept of configurable material to have these different colours or designs...but the code will be the same....its not possible to have a different material code in PO wrt Contract