3 weeks ago
Good morning, all, In PM module, will I be able to schedule, plan, and assign personnel to plant maintenance work orders, preventative maintenance, etc without HR module? Also known as SAP HCM module?
Hi!
In short: yes, there are ways to do that.
In a more detailed fashion: as always, it depends on what you're after 🙂
First of all, let me point out different levels regarding the assignment of work.
For options 2 and 3, there is a documentation regarding assigning individuals to operations via RSH, which can be found here:
S/4HANA Cloud: https://help.sap.com/docs/SAP_S4HANA_CLOUD/2dfa044a255f49e89a3050daf3c61c11/bd80e60bd9d2448ba31ad0d8...
S/4HANA onPrem/Private Cloud: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/8308e6d301d54584a33cd04a9861bc52/bd80e60bd9d2448ba31...
In FSM, there are multiple concepts, you might want to explore:
Hope this helps!
Regards,
Markus
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
So yes I appreciate both answers, and it looks like this mini HR is the one. Is it mini HR due to the minimal usage?
I was told no for utilizing the HR module, as a work around, I made Mx Techs into workcenters... then replaced the Mn.Wrk.ctr: into them... I don't like it, but, it's what is given me. I really need the metrics and KPIs, like to see everyone and track time on jobs, multiple techs on a call and split them out to cover other calls.
I will have all of this with mini HR, correct? A quick look-through shows it will be necessary for MM module when I finally get that! I will complete a workup on mini HR and bring that forward.
THANK YOU ALL, tuts, articles, howtos, and anything will be helpful...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
8 | |
7 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.