Planning Strategy 82

Former Member
0 Kudos

Hi Guys,

Our client requirement is to create planned order after MRP run if the dependent materials are not available when creating sales order while using strategy 82(normally production order gets created while sales order is generated)

Please suggest a solution to resolve this issue, also suggest any additional strategy groups shall be required with any new combinations to achieve this.

Thanks

S Murali

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Thanks

Former Member
0 Kudos

Hi,

Copy this 82 strategy and create new one with requirement types for customer reqt tab as following setting

requirement type - KMSE and treqt class 200 , i think this will definately help you to create planned order. Try and let me know.

Thanks & Regards,

Vijay Patil