Dear All,

Scnerio-

FERT - with strategy 30, BOM component HALB

PIR ( FERT )- 100

Customer Order ( Sales Order ) - 20

After doing MRP run ,MD04 showing Planned order of 120.

As far I know.in strategy 30 PIR does not play any role in MRP run.Pls clear this concept.

Regards,

Praveen

View Entire Topic
rupesh_brahmankar3
Active Contributor

Dear,

Both PIR & sales order requirements will taken by MRP

With strategy 30 you can work with PIRs (demand without reference to customers) as well as with sales orders (customer requirements). Here sales orders will not consume your PIRS and you can perform planning annd production in parallel to both PIRs and Sales orders.Example retail industryor automoblie

Production by lot means you can carry out the production for independnet lot sizes for both PIRs and individual sales orders..

Both stocks will be managed individualluy and delivered to warehouse stock. Sales order will reduce once the stock is delivered to sales order and PIRs will reeduce when stock is delivered to warehouse.

Please refer this link,

http://scn.sap.com/thread/780474


Regards,

R.Brahmankar

UGanesh
Newcomer
0 Kudos

Hi Sir,

What about Plant stock during planning stratergy 30?