Hi there,

Can any please help me to find the indicator in the material master to plan the stock for a particular storage location seperately ...........

Regards

Kaushik

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

In MRP view 4 , there is a field str location indicator -

Select str location stock planned separately. 3rd option

Regards,

Dharma

kaushik_choudhury2
Active Contributor
0 Kudos

Hi Dharma,

Thanks for your reponse but I am not able to see any field that you have mentioned ......... so I posted this query ........ I am checking the same in ECC 6.0.....

Pls advice me ....

Regards

Kaushik

Former Member
0 Kudos

Hi,

Create one new str location, extend to this material by MMSC.

Now view the same material master by selecting suitable org structure (plant & str location ). It is available in mrp 4 view.

Regards,

Dharma

kaushik_choudhury2
Active Contributor
0 Kudos

Hi there ,

I am tried to see if the field is hidden in the screen variant ....... also I have seen the seletion group & field parameter seeting in SPRO..... but still no sucess........

I am not sure ......but I am not able to see the same

Regards

Kaushik

rammohan_shenoy
Active Contributor
0 Kudos

Kaushik,

The storage location MRP tab ( extra fields ) only appear when you populate both plant & storage location in MM02 ( under Organisational level).

For eg : you have Mat A, plant 3010, storgae location =1000

You want to plan 1000 separately then go to Mm02, populate plant & location1000. You should be able to find the storgae location MRP related fields under MRP4.

I hope this clarifies your issue.

thanks,

Ram

Answers (4)

Answers (4)

Former Member
0 Kudos

Hi

Do you mean that, you want to run the MRP for the Storage Location separately ???

===================================================================

If so, First you have to create MRP AREA of storage location type.

Assign the MRP AREA for the material in Material master( MRP1)

Now, run the MRP with MRP AREA as defined above & Plant for that material.

( In MD02, mention Material -


, MRP AREA----


, PLANT)

Then you can get the Requirements Planning for that material , considering the stock of that storage location.

Regards

BRSR

Former Member
0 Kudos

Hi,

Create MRP Area for the storage location planning.

THnaks

Ravi khurana

Former Member
0 Kudos

Since it is managed at plant/storage location level, then you need to enter both plant and storage location in MM01 or MM02.

Alternatively, MMSC also have the fields (same data table).

Hope it helps.

Former Member
0 Kudos

Hi,

It is the SLoc MRP indicator in MRP 4 view under the Storage Location MRP tab.

Former Member
0 Kudos

hi sheik abdulla,

if you want to see SLoc MRP indicator in MRP view, pls focus on Material Type.

For example, you can choose Raw Material after that you will see this.

regards