Planning Horizon for scheduling parameters for planned order

Former Member
0 Kudos

Hi, All PP Gurus........

1) can you tell me what impact does it make if i maintain planning hoirizon days in detailed schldng in OPU5.

What if i ll keep that field blank?

2) what are the prequisite setting for Capacity planning for work centers?

3)what is evaluation time profile for capacity?

Rgds,

Yogesh thorat.........

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

1) can you tell me what impact does it make if i maintain planning hoirizon days in detailed schldng in OPU5.

What if i ll keep that field blank?

If its maintained & if the planned order has start date within this then lead time shceduling is carried out(from routing)

else basic dates are calculated form the in house production time maintained in the material master

Note for the above to happen Scheduling indicator need to be active

2) what are the prequisite setting for Capacity planning for work centers?

You should maintin shift timing,no of individual capacities,capacity utilization,tick the relevant to finite scheduling indicator in capacity tab

3)what is evaluation time profile for capacity?

Here you define the unit of measure,say whether cumulation of ind. capcity to be done or not

You can use the standard evaluation profile available in standard SAP

Hope the above is clear

Revert if you have further query

Regards,

SVP