Planned delivery time in Scheduling agreement and MRP

Former Member
0 Kudos

Hello,

Do you know is it possible to determine system so that MRP run will consider the planned delivery time from the scheduling agreement line instead of material master? Now the system read planned delivery time from material master when creating schedule lines automatically by MRP-run.

Regards, jaana

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

This can be customized in

SAP Customizing Implementation Guide

-> Production

--> Material Requirements Planning

---> Planning

-


> Procurement Proposals

-


> Define External Procurement

Here you can select the indicator "Scheduling according to purchasing info record or agreement" either at plant or MRP group level.

Former Member
0 Kudos

Hi,

Thanks for your answer. I haven't notice that place earlier, but I checked it and it was already determined, but still it does not work correctly. I have sent the question to the SAP.

Regards,

Jaana

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear jaana,

Go to Transaction OMDT and check the Box for

Scheduling according to purchasing info record or agreement

Then system takes from Info-record or SA

Thanks,

Krishna Reddy