Hi,

     I have created one WO with planned delivery time 30 days.For this WO I have created one PR,it is showing today's date as delivery date.There is no  calculation from WO's planned delivery date to PR delivery date.Then what is the use of WO's planned delivery time? please advice me.

With Regards,

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member182535
Active Contributor
0 Kudos

Hi, To calculate the planned delivery time, the system determines the number of days between the order being placed with the vendor and the actual goods receipt for a freely definable combination of vendor, plant, material, purchasing organization and vendor.

former_member196951
Active Participant
0 Kudos

in PR del. date can be derived with Operation Duration eg 720 hrs (1 month). planned delivery time is also populated in PR but del. date not changed accordingly.

jaheer_hussain
Active Contributor
0 Kudos

Hi Parveen,

Thank you.Then what is the use of Planned delivery time in workorder?