Planned delivery cost

Former Member
0 Kudos

Gurus,

I ahve given PDC in PO.When I do the MIRO for PDC the value entered in PO is flowing in MIRO,but the amount & Qty field is blank.What might be the reason?

Edited by: acapulcosdn on May 25, 2010 1:32 PM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

the amount and qty in MIRO will only come if u have done GR

Po and GR done then only qty and Amount with come in MIRO

this is std function of SAP

Same is for Material and PDC

As the logic is that at the time of MIRO how the system will know what amount and qty IV u have recived if GR not done.

If u have done GR than system picks qty form Gr and amount based on PO

hope this helps

Former Member
0 Kudos

HI,

GR has been done.The value in top is showing in -ve for goods in MIRO.

Former Member
0 Kudos

select the INVOICE at the top and not credit memo

in MIRO

or check is PDC MIRO is done in PO history tab

hope this helsp

Former Member
0 Kudos

HI,

In condition type i removed + & - now it is flowing