Hi Gurus,

I am creating external claims in project system and while saving the claim i am getting internal order created as back ground .

When i see the internal order released i am not getting planned costs in internal order as well as in project system.

Regards,

Muralidhar Tallam

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member494495
Active Contributor
0 Kudos

Hi,

Go to KO02

Enter the internal order and Enter

Menu --> Extras --> Cost Analysis

You can see the planned cost

former_member203108
Active Contributor
0 Kudos

Have you done unit costing in the claim?