on 2016 Jan 31 4:16 PM
Hi Experts,
I am doing network costing, and rolling up to WBS through Project simulation, and finally converting it into Operative project.
Now the issue is that suppose
wbs1 - cost plan value = 500,
when i am trying to allocate budget , in cj30, this value is automatically copying into Assigned value.
I have activated the Budget AVAC, with thresholds at 90 percent. Now if i am totaling up planned value and assigning the same to Budget, it is giving Busget exhaust error.
Effectivey, to give a Budget of 500, I have to allocate duble the Budget i.e. 1000 ( to counter the assigned values coming by Planned values (from networks cost).
If the system is behaving normally, then how should I be able to arrive at cost planning and give budget accordingly with AVAC.
PLease reply with your inputs.
Regards
Rohit
Request clarification before answering.
Hi Rohit,
Check the settings for network type->make tick mark in planning and try Budgeting.
Regards,
Seshagiri
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
106 | |
39 | |
6 | |
5 | |
4 | |
3 | |
3 | |
2 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.