Plan cost of activities in COR3

Former Member
0 Kudos

Hi :

I want to know how is plan cost of activities which is displayed in COR3 cost analysis view is arrived at. Please guide me. For RM i know it MAPx planned qty but what about plan costs for activities like FOH,VOH and FOH.

Br

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member309133
Active Contributor
0 Kudos

It should be the plan rate as per KP26 multiplied by the quatity as per the routing.

Sangram

Former Member
0 Kudos

Hi:

In my case in C203 i see 6 BH per hour are planned . My plan rate as determined for the cost center attached to the work center is 20000 Rs/Hour. I processed 12 BH in process order .So plan cost should be 20000*2 hours but it is not.

Regards

former_member309133
Active Contributor
0 Kudos

The plan hour will as per the routing. The actual hrs. may differ. This is reflected in variance calculation.

Sangram

Former Member
0 Kudos

Hai

Run standard costing for all FERT and HAWA and relese standard cost price. You can see target cost in COR3.

Please ensure that KP26 price for all activities is filled.

Pushkala

Former Member
0 Kudos

Dear:

Target costs are calculated upon GR from Process order. I am asking about planned activity costs calculation in process order..

Br