PIRs in Alt. UOM

Former Member
0 Kudos

Is it possible to maintain PIRs in Alternate unit of measure, If yes How

Currently, In MD61 the Unit of measure is greyed out (with Base unit of measure)

but I would like to maintain PIRs in Alt. UOM

Thanks!!

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

It is not possible to use the Alt.UOM for PIR.

But you can set AIT.UOM in Mat.master Basic data 1>Additional data> UOM.

Also set order unit in Purchsing view as per your requirement.

It will help you at the time of Production order & Purchase order creation as order unit is as per your requirement.

Hope it will clear you.

Regards,

Mukesh

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Eshwer,

I had a similar kind of requirement. In MD61 PIRs can only be updated in Base Unit of Measure.

Its not possible to change it. Infact, a note from SAP is also available mentioning that its not possible.

former_member196398
Active Contributor
0 Kudos

Eshwer,

To my knowledge it is not possible to change the unit of measure from Base Unit Of Measure to any other in MD61.

Regards,

Prasobh

Former Member
0 Kudos

Thanks!!