How I can make sure planned independent requirement should not considered in stock transfer ( Intra and inter both ) and Production Order ? We want only it should consider sales orders.
Hello Kawal
Please read carefully the following note, that explains how you can control the reduction of PIRs for STOs:
1819952 | Stock transfer: Control the reduction of Planned Independent Requirements |
You can find this and other useful PP-MP-DEM notes on the following document:
http://scn.sap.com/docs/DOC-46812
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Caetano,
Thanks for the response ! I followed the note and try to do config change as it was mentioned in the note. I made the following change in OVZI . Before VSF and value 1 was not assigned to item category ULN.. Still PIR is considering the STO and material master has strategy 40 assigned to it.
ULN | VSF | 1 | Planning with final assembly |
Hello,
In standard SAP, stock transfers do not consume PIR. Make sure the BAdI MD_PIR_FLEX_CONS is not implemented.
So standard strategy 40 with suitable consumption parameters should suffice the requirement.
Please check the SAP help documentation for strategy 40:
Planning with Final Assembly (40) - Demand Management (PP-MP-DEM) - SAP Library
Best Regards,
Rajen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
10 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.