PIR and STO

Former Member
0 Kudos
829

How I can make sure planned independent requirement should not considered in stock transfer ( Intra and inter both ) and  Production Order  ? We want only it should consider sales orders.

Accepted Solutions (0)

Answers (2)

Answers (2)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Kawal

Please read carefully the following note, that explains how you can control the reduction of PIRs for STOs:

1819952Stock transfer: Control the reduction of Planned Independent Requirements

You can find this and other useful PP-MP-DEM notes on the following document:

http://scn.sap.com/docs/DOC-46812

BR

Caetano

Former Member
0 Kudos

Caetano,

Thanks for the response ! I followed the note and try to do config change as it was mentioned in the note. I made the following change in OVZI . Before VSF and value 1 was not assigned to item category ULN.. Still PIR is considering the STO and material master has strategy 40 assigned to it.

ULNVSF1Planning with final assembly
former_member208398
Active Contributor
0 Kudos

Hello,

In standard SAP, stock transfers do not consume PIR. Make sure the BAdI MD_PIR_FLEX_CONS is not implemented.

So standard strategy 40 with suitable consumption parameters should suffice the requirement.

Please check the SAP help documentation for strategy 40:

Planning with Final Assembly (40) - Demand Management (PP-MP-DEM) - SAP Library

Best Regards,

Rajen