Partial Confirmations of an operation

Former Member
0 Kudos
89

Dear All,

I created an production order and I want to confirm partial quantity of an operation.

But when I chose partial confirmation, and I put the partial quantity, the system didn't suggest the new time for confirmation. I must to calculate the time, for this partial quantity, and put the value in SAP.

It's possible to automate this process?

Thank you very much for your answer!

Regards,

Marian

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Please check transaction OPK4,operation indiv. entry using initial screen.

Answers (1)

Answers (1)

former_member206980
Active Participant
0 Kudos

Hi,

Go to OPK0, Single screen entry (sp001)

Check area of selection :-- header area/ area

Default Values confirmation type ::-partial confirmation

quatity and services:-- immediate proposal

Regards