Dear all ,
I have a requirement that I need to over write the delivery data which automatically comes through PR while creating PO in ME29n at line item level. How can we achieve this using ME_PROCESS_PO_CUST .
which method do we implement.
thanks .
You can explore ME_PROCESS_PO_CUST badi to change the delivery date at time of creation of purchase order. I will not recommend changing the delivery date or any data at time of release. If you clear segregation of duties and field selections then user should not able change the any data in PO at time of release.