on 2015 Aug 12 12:18 PM
Dear all ,
I have a requirement that I need to over write the delivery data which automatically comes through PR while creating PO in ME29n at line item level. How can we achieve this using ME_PROCESS_PO_CUST .
which method do we implement.
thanks .
On what info do you know better than the requisitioner what the desired delivery date is?
And why does an approver know this better than the requisitioner and the buyer, as ME29N is a transaction to approve a purchase order.
If you have the answer to these questions, then you just need to build your logic.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Before the PR is getting converted to PO for approval the delivery date should picks - How system will be knowing when PO is getting created which in turn decide the delivery date
Better as you have logic- you can go for development where proposing Delivery date in PO = PO creation date + Lead time from material master from MRP2 tab on creation of Auto PO in t.code: ME59N from a PR.
Regards,
Biju K
All delay from converting the requisition into a PO and get it approved has to be covered in the purchasing processing time (customizing per purchasing org) which is considered in the planning as well.
If you permanently change the delivery date for raw materials then it will have effects on the planning for your finished goods as well, if they are not rescheduled then it might result in new requisitions for the original delivery date in the next planning run