Hi All,

Currently we have one Overheard % rate for each plant and client like to implement two % Overhead rates in each plant.

How can i achieve this cost sheet percententage based O/H with dependency "D020" for each plant 2 separate rates.

basic idea is to apply different Overhead % rates to different materials.

Any help is appreciated....

Thanks,

Anusha

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

I think it's better to use dependency D010. That way you can create 2 overhead rates with different overhead keys and assign both overhead rates to your costing sheet. Then assign the overhead keys to overhead groups for each plant (t-code OKZ2). Now assign the correct overhead group to each material on the costing 1 view of the material master. The system will determine which overhead rate to use based on the overhead group assigned to the material.